Activities |
Beginn |
Scheduled Duration in hour |
Percent Accomplished |
Remark |
0 Start |
21.10.2021 |
|
|
Milestone |
1 Task Selection |
From 21.10.2021 |
|
|
|
2 Define |
|
|
|
|
2.1 Introduction |
4.11.2021 |
1 |
100% |
|
2.2 Problem Statement |
4.11.2021 |
1 |
100% |
|
2.3 State of Technology |
4.11.2021 |
0.5 |
100% |
|
2.4 Task Description |
5.11.2021 |
0.5 |
100% |
|
2.5 Mindmap |
5.11.2021 |
1.5 |
100% |
|
2.6 Project Plan |
6.11.2021 |
3 |
100% |
|
2.7 Requirement List |
6.11.2021 |
3 |
100% |
|
3 Concept |
|
|
|
|
3.1 Black-box |
6.11.2021 |
1.5 |
100% |
|
3.2 Functional Structure |
6.11.2021 |
3 |
100% |
|
3.3 Morphology |
10.11.2021 |
2 |
100% |
|
3.4 Advantages/Disadvantages |
19.11.2021 |
2 |
100% |
|
3.5 Alternative Solutions |
19.11.2021 |
3 |
100% |
|
3.6 Ranking |
28.11.2021 |
3 |
100% |
|
3.7 Analysis Result |
28.11.2021 |
1.5 |
100% |
|
3.8 Concept Development |
28.11.2021 |
2 |
100% |
|
3.9 Order List |
- |
- |
- |
|
4 Development |
|
|
|
|
4.1 Selected Solution |
|
|
|
|
4.2 Block Diagram |
14.11.2021 |
1 |
100% |
|
4.3 Software Documentation |
19.11.2021 |
1 |
100% |
|
4.4 Pins Allocation Plan |
19.11.2021 |
1 |
100% |
|
4.5 Schematic Diagram |
28.11.2021 |
2 |
100% |
|
4.6 Layout |
|
|
|
|
4.7 Source Code |
28.11.2021 |
0.5 |
100% |
|
4.8 Mechanical |
10.112021 |
6 |
100% |
|
4.9 3D-Print |
- |
- |
- |
|
4.10 Assembly |
10.11.2021 |
5 |
100% |
|
4.11 Testing Phase |
19.11.2021 |
24 |
100% |
|
5 Documentation |
|
|
|
|
5.1 Operating Manual |
28.11.2021 |
3.5 |
100% |
|
5.2 Enhancements |
24.11.2021 |
1 |
100% |
|
5.3 Link List / Literature |
24.11.2021 |
1 |
100% |
|
5.4 Conclusion |
28.11.2021 |
1 |
100% |
|
5.5 Appendix |
- |
- |
- |
|
5.6 Log |
29.11.2021 |
0.5 |
100% |
|
|
|
|
|
|
Presentation |
|
|
|
Milestone |
|
|
|
|
|
Project End |
17.12.2021 |
|
|
|
|
|
|
|
|
Total |
|
76 |
|
|
|
|
|
|
|